DESIGN SCHEDULE PROCUREMENT & CONSTRUCTION SCHEDULE
● Identify decisions to be made and the time required to make these decisions. ● Calculate bid date and completion date
● Calculate the Project Completion Date ● Calculate the start and finish of a specific activity
● Track the status of the design. ● Provides a tool for coordination between the trades
● Provides a baseline to measure progress ● Useful tool to Predict and calculate cash flow
● Evaluate the effect of changes
● Identify the critical activities to keep the project on schedule
● Determines if the contractor has a reasonably accurate and realistic plan
● Verify delay claims
● Serves as an effective project monitoring tool