DESIGN SCHEDULE                                                    PROCUREMENT & CONSTRUCTION SCHEDULE
          ●  Identify decisions to be made and the time required to make these decisions.    ●  Calculate bid date and completion date
          ●  Calculate the Project Completion Date                            ●  Calculate the start and finish of a specific activity
          ●  Track the status of the design.                                  ●  Provides a tool for coordination between the trades
          ●  Provides a baseline to measure progress                          ●  Useful tool to Predict and calculate cash flow
                                                                              ●  Evaluate the effect of changes
                                                                              ●  Identify the critical activities to keep the project on schedule
                                                                              ●  Determines if the contractor has a reasonably accurate and realistic plan
                                                                              ●  Verify delay claims
                                                                              ●  Serves as an effective project monitoring tool