IN AN EFFORT TO INSURE THAT A PROJECT IS COMPLETED WITHOUT MAJOR DEVIATIONS,
SCHEDULES ARE REQUIRED TO ANSWER THE WHEN QUESTION.
Master Schedule - provides a summarized view of the entire project rolled up into one schedule without the detail of a
specific phase of the project. It allows the project team to review the relationships between the phases of the project. It
provides the team a view of the entire project duration for future planning.used in conjunction with the budget to create
cash flow projections. The following two charts provide an example of how scheduling can be helpful.
101